Cambodia Power Development Master Plan 2022-2040 (PDP)

Country : Cambodia
Topic : Electricity
Policy Type : Power Development Plan
Status : Under Implementation
Description:
  • Coal:
    • 2030: 1,558 MW (27.7% of total mix)
    • 2040: 2,973 MW (21.4% of total mix)
  • Fuel Oils:
    • 2030: 490 MW (8.7% of total mix)
    • 2040: 490 MW (4.6% of total mix)
  • Solar:
    • 2030: 1,005 MW (17.9% of total mix)
    • 2040: 3,155 MW (29.8% of total mix)
  • Hydropower:
    • 2030: 1,558 MW (27.7% of total mix)
    • 2040: 2,973 MW (21.4% of total mix)
  • Biomass:
    • 2030: 98 MW (1.7% of total mix)
    • 2040: 198 MW (1.9% of total mix)
  • Battery Energy Storage Systems:
    • 2030: 200 MW (3.6% of total mix)
    • 2040: 420 MW (5.8% of total mix)
  • Natural Gas:
    • 2030: None
    • 2040: 900 MW (8.5% of total mix)
    Time of Issuance : 2022
    Institution : Ministry of Mines and Energy